Openstack Next Steps

Registered by Chuck Short on 2011-10-20

The purpose of blueprint will keep track of the work needed to be done for integrating the Essex release into Precise.

Blueprint information

Status:
Complete
Approver:
Dave Walker
Priority:
Essential
Drafter:
None
Direction:
Needs approval
Assignee:
Chuck Short
Definition:
Approved
Series goal:
Accepted for precise
Implementation:
Implemented
Milestone target:
milestone icon ubuntu-12.04
Started by
Robbie Williamson on 2012-04-26
Completed by
Robbie Williamson on 2012-04-26

Related branches

Sprints

Whiteboard

Etherpad:
  edit: http://pad.ubuntu.com/uds-p-servercloud-p-openstack
  time slider: http://pad.ubuntu.com/ep/pad/view/uds-p-servercloud-p-openstack/latest

- add some mechanism to promote ubuntu images, options:
  - populate ubuntu images upon glance installation
  - option in dashboard to download/install

Work Items:
[zulcss] Package Nova Essex: DONE
[zulcss] Package Swift Essex: DONE
[zulcss] Package Glance Essex: DONE
[zulcss] Package Keystone Essex: DONE
[zulcss] Package Horizon Essex: DONE
[zulcss] Week 6 package weekly snapshot of Nova, Swift, Glance, Horizon: DONE
[zulcss] Week 7 package weekly snapshot of Nova, Swift, Glance, Horizon: DONE
Week 8 package weekly snapshot of Nova, Swift, Glance, Horizon: DONE
Week 10 package weekly snapshot of Nova, Swift, Glance, Horizon: DONE
Week 11 package weekly snapshot of Nova, Swift, Glance, Horizon: DONE
Week 12 package weekly snapshot of Nova, Swift, Glance, Horizon: DONE
Week 13 package weekly snapshot of Nova, Swift, Glance, Horizon: DONE
Week 14 package weekly snapshot of Nova, Swift, Glance, Horizon: DONE
Week 15 package weekly snapshot of Nova, Swift, Glance, Horizon: DONE
Week 16 package weekly snapshot of Nova, Swift, Glance, Horizon: DONE
Week 17 package weekly snapshot of Nova, Swift, Glance, Horizon: DONE
Week 18 package weekly snapshot of Nova, Swift, Glance, Horizon: DONE
Week 19 package weekly snapshot of Nova, Swift, Glance, Horizon: DONE
Week 20 package weekly snapshot of Nova, Swift, Glance, Horizon: DONE
Week 21 package weekly snapshot of Nova, Swift, Glance, Horizon: DONE
Week 22 package weekly snapshot of Nova, Swift, Glance, Horizon: DONE
Week 23 package weekly snapshot of Nova, Swift, Glance, Horizon: DONE
Week 24 package weekly snapshot of Nova, Swift, Glance, Horizon: DONE
Evaluate and package melange for Universe: DONE
Package quantum for Universe: DONE
MIR for keystone: DONE
MIR for horizon: DONE
Enable SSL for Nova: POSTPONED
Enable SSL for Glance: POSTPONED
Make sure Nova configuration is sane: DONE
Make sure Glance configuration is sane: DONE
Investigate S3 for Glance: TODO
Make sure all services are using upstart: DONE
[zulcss] Start Nova EC2 API team: DONE
Fix keystone to use with EC2: DONE
Fix EC2 Bugs: DONE
Solve EC2 ID issue (to allow multiple zones): TODO
[racb] Test ARM/LXC support: TODO
Fix Openstack Bug #: POSTPONED
Test IPV6 on Nova: TODO
Check on Nova auditing and billing: DONE
Test Nova with a large number of instances: INPROGRESS
Test Nova with a large load: INPROGRESS
Test Nova with large uptime: INPROGRESS
Fix nova-lxc Bug #: POSTPONED
Investigate automatic sync/awareness of cloud-images content: POSTPONED
Implement horizon awareness of cloud-images content: POSTPONED
Implement automatic sync of cloud-images content: POSTPONED
Package horizon awareness of cloud-images content: POSTPONED
Package automatic sync of cloud-images content: POSTPONED

Work Items:

(?)

Work Items

Dependency tree

* Blueprints in grey have been implemented.