Staffing the +1 maintenance team for Quantal
Registered by
Steve Langasek
Discuss staffing of the +1 maintenance team for Q, to make sure we have a full roster.
Blueprint information
- Status:
- Complete
- Approver:
- Steve Langasek
- Priority:
- High
- Drafter:
- Colin Watson
- Direction:
- Needs approval
- Assignee:
- Colin Watson
- Definition:
- Approved
- Series goal:
- Accepted for quantal
- Implementation:
-
Informational
- Milestone target:
-
ubuntu-12.10-beta-2
- Started by
- Colin Watson
- Completed by
- Colin Watson
Whiteboard
(?)
Work Items
Work items:
[cjwatson] engage the community team around this: POSTPONED
[seb128] talk to Didier: DONE
[vorlon] talk to Jason about desktopers: DONE
[vorlon] talk to Jose about L3ers: DONE
[cjwatson] talk to Max and Pete: POSTPONED
[rick-rickspencer3] talk to Victor re Kamal et al: DONE
[cjwatson] linkify the priority list: DONE
[rick-rickspencer3] talk to James and Antonio: DONE
[davewalker] talk to two people on his team about sharing a shift: DONE
Dependency tree

* Blueprints in grey have been implemented.