Transiesta calculation was a Gamma calculation while you request transmission k-points

Registered by Sandra Rodriguez

We encountered the following error in a TBTrans calculation: "Transiesta calculation was a Gamma calculation while you request transmission k-points". We are unsure of the cause. The TranSIesta calculation was performed using a 1 × 9 × 9 k-grid, and for the TBTrans calculation, we specified a 1 × 20 × 20 k-grid. The transport direction is x.

Let's see if someone can help us. Thanks