Work items:
[billy-olsen] Establish version format: DONE
[hopem] Create milestones: DONE
[hopem] Add virsh pool check: DONE
[hopem] Create debian packaging source: DONE
[hopem] Adapt maas-deployer source for packaging: DONE
[hopem] Update README: DONE