Test and validate the big.LITTLE ARM Reference Switcher, integrated with Fast Model and running with the Ubuntu based rootfs.
Test steps and descriptions for the ARM Reference Switcher described at:
https:/
Goals:
- Automate and execute the test cases and scenarios described at https:/
- Report back all issues at the ARM Reference Switcher project
- Integrate the automated test cases at Lava, for continuous validation and further validation with the Integrated Switcher
Continued from https:/
Blueprint information
- Status:
- Complete
- Approver:
- Ricardo Salveti
- Priority:
- High
- Drafter:
- Ricardo Salveti
- Direction:
- Approved
- Assignee:
- Avik Sil
- Definition:
- Approved
- Series goal:
- Accepted for trunk
- Implementation:
-
Implemented
- Milestone target:
-
12.05
- Started by
- Ricardo Salveti
- Completed by
- Ricardo Salveti
Related branches
Related bugs
Sprints
Whiteboard
[rsalveti, May 3, 2012] Avik, please update the WIs based on what needs to be done/completed over this cycle.
[aviksil, May 24, 2012], Postponing last two work items after discussing with Paul
[rsalveti, May 31, 2012] Marking it as implemented, as it was properly tested and reported to the big.little project team.
Meta:
Roadmap id: KWG2012-
Headline: big.LITTLE ARM Reference/
Acceptance: Test big.LITTLE on the A15/A7 simulator running the Ubuntu based rootfs (nano) with the set of test cases described at the test plan.
Milestones:
ARM reference Switcher 3/15/2012
Validation Ready 3/29/2012
Validate Reference Switcher 4/5/2012
Linux Integrated Switcher 4/5/2012
Validate Integrated Switcher 4/26/2012
Release Candidate 1 (RC1) 5/10/2012
General Availability (GA) 5/31/2012
Execution matrix;
https:/
Work Items
Work items:
Test boot-a7: DONE
Test switcher-unit-tests Integrated (5/02/2012): DONE
Test boot-a7 Integrated (5/02/2012): DONE
Test boot-a15 Integrated (5/02/2012): DONE
Test mem-stress-a7 Integrated (5/02/2012): DONE
Test mem-stress-a15 Integrated (5/02/2012): DONE
Test disk-io-stress-a7 Integrated (5/02/2012): DONE
Test disk-io-stress-a15 Integrated (5/02/2012): DONE
Test data-corruption-a7 Integrated (5/02/2012): DONE
Test data-corruption-a15 Integrated (5/02/2012): DONE
Test data-corruption
Test cache-coherency-a7 Integrated (5/02/2012): DONE
Test cache-coherency-a15 Integrated (5/02/2012): DONE
Test cache-coherency
Test mem-stress-
Test disk-io-
Find what tests would be useful to be automated on lava-tests: POSTPONED
Integrate the test cases with lava-tests: POSTPONED