Test and validate the big.LITTLE ARM Reference Switcher, integrated with Fast Model and running with the Ubuntu based rootfs.

Test steps and descriptions for the ARM Reference Switcher described at:
https://docs.google.com/a/linaro.org/document/d/14Kta4wQ0QdKlO_iQ41EolkLm-pxw_Ggh_OW-ca6BEvM

Goals:
 - Automate and execute the test cases and scenarios described at https://docs.google.com/a/linaro.org/spreadsheet/ccc?key=0AroPySpr4FnEdGttYkhCUGVzZ2JOS0tGaU1QUm9wOHc#gid=0
 - Report back all issues at the ARM Reference Switcher project
 - Integrate the automated test cases at Lava, for continuous validation and further validation with the Integrated Switcher

Continued from https://blueprints.launchpad.net/linaro-ubuntu/+spec/ubuntu-test-validation-biglittle-arm-reference-switcher.1

Blueprint information

Status:
Complete
Approver:
Ricardo Salveti
Priority:
High
Drafter:
Ricardo Salveti
Direction:
Approved
Assignee:
Avik Sil
Definition:
Approved
Series goal:
Accepted for trunk
Implementation:
Implemented
Milestone target:
milestone icon 12.05
Started by
Ricardo Salveti
Completed by
Ricardo Salveti

Related branches

Sprints

Whiteboard

[rsalveti, May 3, 2012] Avik, please update the WIs based on what needs to be done/completed over this cycle.
[aviksil, May 24, 2012], Postponing last two work items after discussing with Paul
[rsalveti, May 31, 2012] Marking it as implemented, as it was properly tested and reported to the big.little project team.

Meta:
Roadmap id: KWG2012-BIG-LITTLE-MIGRATION
Headline: big.LITTLE ARM Reference/Integrated Switcher has been validated and tested with the Ubuntu based rootfs on a ARM Fast Model (12.05 Cycle)
Acceptance: Test big.LITTLE on the A15/A7 simulator running the Ubuntu based rootfs (nano) with the set of test cases described at the test plan.

Milestones:
ARM reference Switcher 3/15/2012
Validation Ready 3/29/2012
Validate Reference Switcher 4/5/2012
Linux Integrated Switcher 4/5/2012
Validate Integrated Switcher 4/26/2012
Release Candidate 1 (RC1) 5/10/2012
General Availability (GA) 5/31/2012

Execution matrix;
https://docs.google.com/a/linaro.org/spreadsheet/ccc?key=0AroPySpr4FnEdGttYkhCUGVzZ2JOS0tGaU1QUm9wOHc#gid=0

(?)

Work Items

Work items:
Test boot-a7: DONE
Test switcher-unit-tests Integrated (5/02/2012): DONE
Test boot-a7 Integrated (5/02/2012): DONE
Test boot-a15 Integrated (5/02/2012): DONE
Test mem-stress-a7 Integrated (5/02/2012): DONE
Test mem-stress-a15 Integrated (5/02/2012): DONE
Test disk-io-stress-a7 Integrated (5/02/2012): DONE
Test disk-io-stress-a15 Integrated (5/02/2012): DONE
Test data-corruption-a7 Integrated (5/02/2012): DONE
Test data-corruption-a15 Integrated (5/02/2012): DONE
Test data-corruption-switching Integrated (5/02/2012): DONE
Test cache-coherency-a7 Integrated (5/02/2012): DONE
Test cache-coherency-a15 Integrated (5/02/2012): DONE
Test cache-coherency-switching Integrated (5/02/2012): DONE
Test mem-stress-switching Integrated (5/02/2012): DONE
Test disk-io-stress-switching Integrated (5/02/2012): DONE
Find what tests would be useful to be automated on lava-tests: POSTPONED
Integrate the test cases with lava-tests: POSTPONED

Dependency tree

* Blueprints in grey have been implemented.

This blueprint contains Public information 
Everyone can see this information.