There are three test categories in Linaro QA team per month: Daily, Weekly and Monthly. This Blueprint is used for Linaro 13.02 monthly release test.
Blueprint information
- Status:
- Complete
- Approver:
- Alexander Sack
- Priority:
- Essential
- Drafter:
- Botao
- Direction:
- Needs approval
- Assignee:
- Botao
- Definition:
- New
- Series goal:
- None
- Implementation:
- Implemented
- Milestone target:
- 2013.02
- Started by
- Botao
- Completed by
- Soumya Basak
Related branches
Related bugs
Sprints
Whiteboard
Meta:
Headline: Monthly release test for Linaro 13.02.
Acceptance: Finish the monthly release test for Linaro 13.02 cycle.
Linaro 13.02 Release Day: 28 February 2013
[28 Feb 2013, soumya-basak]: Linaro-android 13.02 release critical test has been done. Send summary report to the release team.
[28 Feb 2013,soumya-basak]: Linaro OE engineering build 13.02 release test has been done. Send summary report to the release team.
[25 Feb 2013,soumya-basak]: Monthly release critical test of OE engineering build started.
[25 Feb 2013, soumya-basak]: Monthly release candidate critical test of Linaro-android for TI-Panda 4430, TI-Panda 4460, ST-Snowball, Origen started.
[28 February 2013, botao-sun] Linaro 13.02 release test has been done, test result summary report has been sent.
[27 February 2013, botao-sun] TI Panda 4460 Linux Linaro ubuntu Quantal won't be released this month, which is caused by a boot failure - Bug 1128853
[25 February 2013, botao-sun] Monthly test for Linaro 13.02 release has started. ARM Versatile Express A9 Linaro Android test has been done.
[3 February 2013, botao-sun] This blueprint has been created.
Work Items
Work items:
[soumya-basak] Add identified Android and Open Embedded release builds to the spreadsheet: DONE
[soumya-basak] Finish release critical test on Android and Open Embedded release candidates: DONE
[soumya-basak] Finish all test on every final release candidate: DONE
[soumya-basak] Send release test summary report to Linaro Release mailing list: DONE
[botao-sun] Add identified Linux Linaro ubuntu Quantal release builds to the spreadsheet: DONE
[botao-sun] Add identified Linaro Android release build for ARM Versatile Express A9 board to the spreadsheet: DONE
[botao-sun] Finish all test on every final release candidate: DONE
[botao-sun] Send release test summary report to Linaro Release mailing list: DONE
[botao-sun] Check http://
[botao-sun] Close the milestone http://