Linaro bl iks 13.02 weekly core test
big.LITTLE IKS core test suite should be executed on TC2 platform with latest IKS Android image.
Blueprint information
- Status:
- Complete
- Approver:
- Alexander Sack
- Priority:
- Essential
- Drafter:
- Naresh Kamboju
- Direction:
- Needs approval
- Assignee:
- Naresh Kamboju
- Definition:
- New
- Series goal:
- None
- Implementation:
- Implemented
- Milestone target:
- 2013.02
- Started by
- Naresh Kamboju
- Completed by
- Naresh Kamboju
Related branches
Related bugs
Sprints
Whiteboard
[nkambo Feb 4 2013]
notes here
[nkambo Feb 28 2013]
bL IKS core test suite executed on each calender week, which includes week-6 to week-9 and results are populated on to the results spreadsheet. this results have been published in Linaro private channel.
Meta:
Roadmap id: BIG_LITTLE_IKS
Headline: Tracking big.LITTLE IKS weekly core test for cycle 13.02.
Acceptance: Finish three weekly test tasks, for calendar week 6, 7, 8 and 9.
Deliverable: Spreadsheet contains all weeks bL IKS core test suite results which include week-6 to week-9 and published these results in private channel. spreadsheet link https:/
Work Items
Work items:
Execute big.little core test suite on Jan week-6: DONE
report bugs if any under https:/
Execute big.little core test suite on Jan week-7: DONE
report bugs if any under https:/
Execute big.little core test suite on Jan week-8: DONE
report bugs if any under https:/
Execute big.little core test suite on Jan week-9: DONE
report bugs if any under https:/