Linaro 11.08 - release tasks tracking

Registered by Fathi Boudra

This BP is tracking the Linaro 11.08 release tasks.

Timeline:
* 1st task blocks is realized at the beginning of the month
* 2nd task blocks is realized a week before components release
* 3rd task block is realized from the RC day (on Monday)

Blueprint information

Status:
Complete
Approver:
Fathi Boudra
Priority:
Essential
Drafter:
Fathi Boudra
Direction:
Approved
Assignee:
Linaro Release Team
Definition:
Approved
Series goal:
Proposed for trunk
Implementation:
Implemented
Milestone target:
milestone icon 2011.08
Started by
Fathi Boudra
Completed by
Fathi Boudra

Related branches

Sprints

Whiteboard

[fboudra, 23 Aug 2011] website update is blocked due to permissions issues.
[fboudra, 24 Aug 2011] Ian fixed the website permissions issues. Downloads page is editable.

Work items (11.08):
Create release wiki page (https://wiki.linaro.org/Cycles/1108/Release): DONE
Create monthly release summary spreadsheet: DONE
Gather milestone pages from PMs/TLs, consolidate on spreadsheet: DONE
Gather a list of people assigned to the release response team: DONE
Gather proposed headlines from PMs, consolidate on release wiki page: DONE
Review proposed headlines, spot outstanding ones, initiate marketing: DONE

Send release dates and deliveries reminder: DONE

Setup QA tracker for RC images: DONE
Setup board support status (BSS) forms: DONE
Send call for testing RC images: DONE
Review tests results from board support status (BSS) forms and LAVA: DONE
Setup releases.linaro.org: DONE
Copy RC images to releases.linaro.org: DONE
Update release wiki page downloads links: DONE
Update website downloads page: DONE
Gather known issues, consolidate on release wiki page: DONE
Write introduction and polish highlights of the release. DONE
[dooferlad] Update linaro-fetch-image-ui configuration file: POSTPONED

(?)