Deploy Calxeda server clusters

Registered by Dave Pigott on 2012-11-28

We have two Calxeda 24 CPU server clusters, which have to be deployed in the lab and made available for LAVA integration work

Blueprint information

Status:
Complete
Approver:
None
Priority:
Medium
Drafter:
None
Direction:
Needs approval
Assignee:
Dave Pigott
Definition:
New
Series goal:
None
Implementation:
Implemented
Milestone target:
milestone icon 2013.01
Started by
Dave Pigott on 2012-12-05
Completed by
Dave Pigott on 2013-01-11

Related branches

Sprints

Whiteboard

[fboudra, 2012-12-20] rack, PDU and support hardware have been purchased. Continue the effort on 2013.01
[dpigott, 2013-01-11] blocked on trying to get cxmanage version for 12.04
[dpigott, 2013-01-11] OK. Got 0.5.1 of cxmanage installed on gateway and it works just fine.

Meta:
Headline: 2 Calxeda Green Boxes deployed in validation lab
Acceptance: The boxes are accessible via ssh at validation.linaro.org and can be managed via IPMI
Roadmap Id: CARD-255

(?)

Work Items

Work items for 2012.12:
Purchase rack, PDU and support hardware: DONE

Work items for 2013.01:
Deploy in new rack: DONE
Configure IP addresses: DONE