Create a budget for the next 12 months for LAVA lab

Registered by Dave Pigott

We currently are working on a continuing budget for the lava lab for the next 12 months so that we can know what we spend and track what we have more thoroughly.

Blueprint information

Status:
Complete
Approver:
None
Priority:
Low
Drafter:
None
Direction:
Approved
Assignee:
Dave Pigott
Definition:
Approved
Series goal:
None
Implementation:
Implemented
Milestone target:
milestone icon 2012.08
Started by
Fathi Boudra
Completed by
Fathi Boudra

Related branches

Sprints

Whiteboard

Meta:
Headline: We need to establish the on-going LAVA budget for the lab for the next 12 months.
Acceptance: Budget established and approved.

(?)

Work Items

Work items:
Create current costing spreadsheet: DONE
Create maintenance budget estimate: DONE
Create budget for new member hardware deployment: DONE

This blueprint contains Public information 
Everyone can see this information.